Posts Tagged ‘Ken Burton Trail’

Ken Burton Trail Restoration – Day 14

Sunday, March 27th, 2016

Saturday, March 19, 2016, was a perfect day to do trailwork. There was moisture in the ground from the week’s rain, temperatures were cool, and the crew were able to ride to and from the work site via the Gabrielino trail. A half-dozen or so volunteers were already on their way to the work site when this group photo was taken.

Some crew members were already on their way to the work site

Some crew members were already on their way to the work site

While several volunteers rode in via the Gabrielino, some opted to ride up to Brown Mountain and enjoy the fruits of their labor on the way down Ken Burton trail to the work site. It was the first time we had been able to ride all the way down to the 16th switchback without interruption. The volunteers who rode down Ken Burton trail were all in agreement that the efforts of the group over the previous five months had been well-worth the experience.

We were fortunate enough to have several SoCal High school league student-athletes and coaches join us for the day, along with members of the IMTBTrails.com mountain bike forum out of Santa Clarita.

This was a heavily damaged section

This was a heavily damaged section

With the major brush work completed, the crew split into groups, concentrated on re-cutting the bench along a heavily damaged section of the trail, restoring outslope, and removing remaining roots and stubs from the tread.

Another crew worked diligently to rebuild the 16th switchback, using rock extracted from the tread to build an outside retaining wall on top of the old wire basket retaining structure that had failed.  By day’s end, the switchback was completely rebuilt. We were fortunate to have the expert assistance of Hans from Bellfree Contractors on this major effort.

Rebuilding Switchback 16

Rebuilding Switchback 16

By day’s end the crew had completed tread work almost all the way down to the 17th switchback, restoring one of the more heavily damaged sections of the trail so far.

So far, 81 individual volunteers have put in 1,408 total person-hours of work on this project in 14 scheduled work days, plus another 12 prep days.  This is an impressive effort to restore this much-loved trail that was built by mountain bikers from the Mount Wilson Bicycling Association in the early 90s.

20160319-Ken Burton Trailwork Progress

The next scheduled group work day on Ken Burton will be with Mount Wilson Bicycling Association on April 17, though there will be additional prep days before then. Contact Steve@corbamtb.com if you’re interested in helping prep before then (likely April 10).

Ken Burton Trail Restoration – Days 12 and 13

Monday, March 14th, 2016

Day 12, March 3, 2016

On Thursday, March 3, CORBA and MWBA Volunteer Sawyers and some additional dedicated volunteers continued work on the Ken Burton trail. This time they started at the bottom of the trail, from its junction with the Gabrielino National Recreation Trail, working up the lower switchbacks through a tangle of downed trees, poison oak, overgrowth, and near-impossible wayfinding. Using chainsaws was the only viable means of cutting through the several fallen oak trees that once shaded this beautiful old oak grove. This shaded oak grove was often a popular spot to re-group after challenging oneself to clean all the switchbacks, before attempting the most difficult between there and the Gabrielino trail.

Steve Messer had spent February 20 flagging out the original trail, using a combination of GPS tracks, searching for ground evidence of dirt compaction that may still be found even after six years, and a good memory of one of his favorite trail loops.

The group made what appeared an impossible task look relatively easy, working carefully to cut brush, downed trees, and have swampers carry away and stash the cuttings. It was most gratifying to follow the string of ribbons, and find the original tread under all that brush and debris. We made it to the 17th switchback, our target for the day.

Day 13, March 13, 2016

Erik from MWBA cuts through the brush

Erik from MWBA cuts through the brush

 

Ten days later, on Sunday, March 13, 2016, was our 13th group trailwork day. It was especially encouraging to see that all our previous work has held up perfectly to the recent rain and storms, with no rutting, and soil being packed down nicely. The first sections we worked on last November are maturing nicely.

Our 13th worday on Sunday March 13, was a milestone day.  With 21 volunteers out putting in a 7 hours or more, we were able to do a first-pass brushing on the last remaining section of trail, linking to our March 3rd work and to the bottom of the trail. This was a great milestone in this restoration project, now in its sixth month. We had cut brush from the entire trail corridor.

While the brushing tools and swampers diligently plugged away to reopen the trail corridor, the tread crew made quick work of the tread on about .3 miles of trail. With the damp dirt, cool temperatures, and sense of determination among the volunteers–many of whom have worked multiple days on this project–we had an extremely productive day.

Ryan and Stephanie work on tread restoration

Ryan and Stephanie work on tread restoration

There is still work to do on the 16th switchback, but it was rendered temporarily passable for the day. The last half mile of the trail is far from finished, needing a second pass with the hedge trimmers and extensive treadwork. But with some careful hike a bike the group was able to ride out the bottom of the trail, completing the loop with the closed Gabrielino trail. It was a truly gratifying day for all who made it.

We currently estimate two to three more days working on the bottom of Ken Burton trail, and an additional day on the Gabrielino trail between Oakwilde/Ken Burton and Paul Little.

We were also joined by an Ultra Distance runner, and past AC100 runner. Many trail runners are just as excited to get this trail opened as mountain bikers. During our last two days of work and long before we were finished brushing the corridor, we had hikers come up from the bottom, bushwhacking their way through until they heard us, then asking where the trail was. After reminding them the trail was closed to the public and we were working as Forest Service volunteers to rebuild it, he headed on beyond our work area for a leisurely stroll up the newly groomed segment of the trail, and all the way to Brown Mountain. People put far too much faith in outdated maps and information.

After loading up tools, the group rode out via the Gabrielino trail back to the trailhead and our meeting spot. This section of the Gabrielino trail was worked on two years ago by Bellfree Contractors. volunteers, and the Los Angeles Conservation Corps with the financial support in the form of an REI grant to CORBA, and funding from the Forest Service for the project. While the section was rebuilt, it has been two years and it also once again needs some minor work.  Between Oakwilde and Bear Canyon the trail is in poor condition and almost entirely gone and unrecognizable for a long stretch. Plans are underway to continue work on rebuilding that section of the Gabrielino, once again in partnership with the LACC, USFS, Bellfree Contractors and REI.

Both the Gabrielino between Paul Little and Bear Canyon junction, and the Ken Burton trail, remain closed to the public by order of the Forest Service. Please respect the closure until the Forest Service opens the trails. We’re just as eager as everyone else to finish the project and be able to ride, but there are many steps to go through before that can happen, and it is the decision of the Forest Service as to when and if the trail will be opened.

2016-03-13--Ken-Burton-Completed-Map

For all the volunteers who have joined us for at least two days, we’ve ordered a special commemorative T-shirts.  It’s our–CORBA and MWBA– way of saying thank you. If you haven’t put in two days, there are a few more coming up starting this weekend and in April.

Ken Burton Restoration Commemmorative T-Shirt

 

Ken Burton Trail Restoration – Days 9 and 10

Tuesday, February 23rd, 2016

 

Restored Switchback, one of 22.

Restored Switchback, one of 22.

2016-02-21 13.06.01

Trailwork Parking

On Sunday, February 7, MWBA hosted a trailwork day on Ken Burton trail. With 16 volunteers, we cleared an additional .18 miles of trail. Heavy winds and dry Santa Ana conditions prevented us from using all our power tools, so progress was slower than previous days. With volunteer help from professional trailbuilder Hans Kiefer of Bellfree Contractors, three large drainages were made more sustainable using rock retaining walls, rock armoring and lots of sweat!  Using rock collected on site saved the crew from having to haul in additional materials for wire basket structures. The crew restored several switchbacks, added drainage, and brushed and cleared an additional quarter mile of trail.

On Sunday, February 21st, we had fourteen volunteers come out to continue restoration efforts. The group rode to the end of upper Brown Mountain fire road, then continued down the already-completed section of the trail. Bikes were left at a convenient point, below which it would have been a strenuous climb to ride back out, especially after working on the trail. We hiked down the rest of the way to the work site.

Mitch (MWBA) and Mike McGuire were able to brush an additional .19 miles of trail with the powered tools. As we get down to lower elevations, the brush is getting much thicker, taking more time and effort to clear. The rest of the crew concentrated on outsloping, drainage and re-establishing tread on approximately .14 miles of trail. The total work day included approximately .33 miles of trailwork.

Swamping the first pass with the hedge trimmers

Swamping the first pass with the hedge trimmers

The last third of a mile of the trail will require chainsaws to clear the many fallen oak trees. Steve Messer, CORBA president and trail crew leader, flagged out the last half mile based on GPS tracks of the trail before the fire. Ken Burton passed through a beautiful shaded oak grove before dropping down to the Gabrielino trail and Oakwilde Campground. Sadly, many of those oaks were killed and have fallen across what was the trail. Brush has grown into this relatively flat section of trail, and will require extensive chainsaw work to clear. We plan to go in with the CORBA/MWBA sawyer crew (USFS certified chainsaw operator volunteers) to clear those trees before the next scheduled trailwork day.

Riding previously restored section after a day's work

Riding previously restored section after a day’s work

With over 1000 volunteer hours, ten workdays, and several additional prep days by CORBA and MWBA trail crew leaders,  we have so far completed or brushed approximately 1.8 miles of the 2.25 mile trail. What’s left is less than a half mile, including extensive chainsaw work. Weather permitting, we’ll be back out there on March 13, 2016.

2016-02-21--Ken-Burton-Completed-Map

Ken Burton Trail Restoration – Day 8

Sunday, January 24th, 2016
Completed trail at the top of the switchbacks

Completed trail at the top of the switchbacks

Sunday, January 24, 2016 we had another successful day of trail restoration. Anyone driving up the Angeles Crest Highway today, who happened to glance across the Arroyo Seco canyon towards Brown Mountain would have seen ten volunteers spread out along the switchbacks, the upper half of which are now clearly visible once again.

Clearing Brush has been a major component of this project

Clearing Brush has been a major component of this project

Scouting the work ahead

Scouting the work ahead

Today we concentrated on brushing the next .25 miles of the trail, which included six switchbacks.  Most of this section has held up extremely well, and only a few places will require rock-armoring and/or drainage restoration.  We took the opportunity to scout and flag the next half mile of trail beyond that, identifying the original trail in places where animals and unauthorized trail users–it is still a closed trail–had created unsustainably steep bypasses around heavy brush and a some rock slides.

Our next trailwork days, tentatively scheduled for February 7, and February 21 (with MWBA) we’ll concentrate on tread work for the section we cleared of brush today. There are no major problem spots along this section. We’ll also continue brushing the trail beyond there to re-establish the trail corridor and better see the condition of the tread. In some sections we scouted, the brush was so thick that there was no way through, forcing us either up the slope or down the slope to get around the brush and back on the remnants of trail tread.

 

Failed switchback #16 will need extensive work

Failed switchback #16 will need extensive work

The biggest problem section will be at the 16th switchback. Here the switchback itself has been washed away, and we’ll need to do extensive rock work to make the section sustainable and rideable. Much of the area is soft, loose dirt, and the trail is completely filled with brush, slough and debris. Nothing our dedicated volunteers can’t handle!

All in a day's work. The hike/ride back out

All in a day’s work. The hike/ride back out

After today’s work, those volunteers who still had time were treated to lunch at a local restaurant. It is the dedication of these volunteers, many of whom have come out every trailwork day we’ve scheduled, that allows us to keep pushing forward to complete the trail. Major kudos to all of you who have contributed!

Click for a larger view.

Ken Burton Trail Restoration – Day 5

Tuesday, January 12th, 2016
The Crew

The Crew

January 10, 2016 was another extremely productive day for the Ken Burton Trail Restoration project.  With recent storms, it was reassuring to see our of work holding up perfectly well. In fact, the restored sections of Ken Burton fared better than the Upper Brown Mountain fire road, which was rutted and much more rocky than before the storms.

2016-01-10 - Retaining wall

Retaining wall crew at work – Photo by Matt Lay

Once again teaming up with the Mount Wilson Bicycling Association, 21 volunteers were able to do a first-pass cutting brush on 0.3 miles of trail, with tread restoration completed on 0.2 miles of that. Matt Lay, of MWBA led the effort to complete the first wire basket retaining wall. At our last day, the lower retaining wall was completed. The upper wall is almost complete, needing a few more hours of work. There are two more retaining wall sections that will need similar rebuilding.

We were blessed with perfect trailwork conditions. Rain was in the forecast for the night before our event, with most forecasts showing the weather tapering off by morning. That’s exactly what we had: nice damp soil, and cool, comfortable work conditions.

The day before the scheduled trailwork, I took a load of tools up via bob trailer, and did a walk-through video of the section we were to work on. After the trailwork day was completed, I repeated the video walk-through. The before and after videos show what an amazing transformation is possible. The two videos are embedded below.

We also have to thank Pat Phillips, a long-time trailwork volunteer and supporter who helped build the trail in the 90s. He graciously hosted us once again for lunch after the day’s work.

Mount Wilson Bicycling Association will be hosting the next trailwork day on Ken Burton this coming Sunday, January 17. and  CORBA will host again on January 24 (both dates are weather-permitting). We all want to see this trail restored and opened!

Thanks once again to the tremendous volunteers for their hard work and dedication.

Ahead, brush. Behind, a trail.

Ahead, brush. Behind, a trail.

 

Progress:

Progress!

Progress!  (Click for a larger view)

 

(more…)

Ken Burton Trail Restoration Continues December 13

Wednesday, November 25th, 2015
MWBA and CORBA Trail Crew

Most of the Sunday, 11/22 crew after they arrived. Thanks guys and gals!

On Sunday, November 22nd, 2015, we had our third full trail restoration work day on Ken Burton trail with the Mount Wilson Bicycling Association. 23 volunteers made the 7 mile, 2000′ climb to pitch in. Bob trailers were used once again to get needed tools and supplies to the work site.

We continued on from where we finished last time. The crews worked feverishly for a solid four hours, clearing an additional 1600′ of trail. We’re making rapid progress, thanks in part to the excellent original construction by the Mount Wilson Bicycling Association in the 1990’s.

 

Ken Burton Hike a Bike

Before: A group who poached the closed trail in 2013. The brush is only thicker and taller now.

 

Completed trailwork Ken Burton

After our crew had been through

 

Ken Burton Trail Restoration

After: looking the other direction

The before and after is quite dramatic. Where the trail was previously completely obscured by brush, it is now in better shape than before the fire. Our crews are getting it down to a fine art. We’re using power hedge trimmers for the initial brush clearance, followed by swampers (who remove and stash the cut brush), then loppers and hand saws to fine tune the brush and stump removal.  The lead crew is followed by a tread crew, working to remove stumps and roots from the tread, and pull down slough to restore the original trail tread.  We’re cutting the trail to its original 36 – 48″ tread width where possible, knowing that it will narrow down again with time.

Ken Burton Trailwork

Getting close to the memorial and the top of the switchbacks

 

Ken Burton Memorial. Plaque has been long gone.

Ken Burton Memorial. The plaque is long gone.

Our target for the day was to reach the Ken Burton Memorial, a plaque dedicated to USFS Battalion Chief Ken Burton, who was killed in a car crash in November 1985. For those who remember the trail, the memorial was just before the very first switchback descending into the Arroyo Seco canyon. We made it to the Memorial at about 1 p.m., leaving time for people to gather tools, load up trailers and ride back down for lunch at 2. Pat Phillips, a local Altadena resident and one of the original construction crew in the 1990’s, graciously hosted us for lunch afterwards.

Failed wire basket retaining wall

Failed wire basket retaining wall

 

We’ve also reached the first failed retaining wall structure. In my survey of the trail, only two sections of retaining wall structure failed out of the dozens used, a testament to the work of the original MWBA crew. Those dozens of structures have survived three major El Nino winters and one Station Fire.

Completed-Map

Project Status. Click for a larger view.

So far we’ve cleared approximately .7 miles of the trail, about 1/3 of the work. We have a couple more days of very similar work before it will get especially thick and tough near the bottom. At that time we’ll need to coordinate with the Los Angeles Conservation Corps who are working on the Gabrielino trail, near where it meets the bottom of Ken Burton trail.

Thanks again to all the volunteers who came out to help. Our next work day is December 13 (weather permitting). Our tentative dates starting next year are January 10 and January 24, to be confirmed soon. The more people who contribute, the better our chances of riding this trail next summer!