Sullivan Canyon Closure Update

From Sharon O’Rourke of The Gas Company

As of Friday, June 4th, we completed the initial access road repair work.  Access from Mulholland was re-opened to the public as of Saturday, June 5th.

On Wednesday, June 23rd, we will start the pipeline protection work which will include the final planned access road repairs and covering the remaining pipeline exposure areas with the concrete mats.  This will require closing public access to Sullivan Canyon at both Mulholland and Queensferry Road.  The closure is necessary for public safety due to the equipment needed for the placement of the mats.   The work is estimated to take 3-4 months.

Update August 31: Apparently the canyon will be closed until November 12th.

Comments are closed.